Case Study on the Removal of a Drill-Free Jacket and Platform Decommissioning: Malaysia's South Angsi Alpha (SAA) Platform

Aug 18, 2026

Leave a message

xavier
xavier
Documentary Service Manager-Logistics/Sales Manager-Europe

In 2025, the decommissioning project for the South Angsi Alpha (SAA) platform off the coast of Terengganu, Malaysia, fully showcased the huge advantages of rigless decommissioning technology. By avoiding the use of expensive heavy-lift vessels and drilling rigs, the project team successfully delivered Malaysia's largest 'rig-to-reef' decommissioning project, achieving minimal delays, efficient collaboration, and maximum cost-effectiveness.

This case study explores how a rigless solution-including reverse installation methods, custom lifting systems, and ROV-assisted underwater cutting-successfully completed the decommissioning of a 4,000-ton platform, setting a new benchmark for responsible offshore decommissioning in Southeast Asia.

 

1

 

 

1. Project Overview 

Project

South Angsi Alpha (SAA) Platform Decommissioning

Location

130 km off the Terengganu coast, Malaysia

Platform Type

4,000-metric-ton, four-legged Mobile Offshore Application Barge (MOAB)

Water Depth

Approximately 70 meters

Project Scale

Largest decommissioning and reefing operation in Malaysian waters

 2. Drill-free solution: How to make it happen

Reversed Installation Method

Marine Masters used the reversed installation method-essentially running the installation process in reverse-to remove the MOAB. This approach eliminated the need for heavy-lift vessels by using the platform's own structural integrity and carefully planned load transfers.

Marine Masters.

Custom-Designed Lifting Systems 

The project developed custom-designed lifting systems specifically to avoid the use of expensive heavy-lift vessels. These systems were engineered to work within the platform's space and load constraints.

ROV-Assisted Underwater Cutting

Multiple cutting-edge techniques were deployed for underwater operations:
 

Remotely operated underwater cutting (assisted by ROVs) 

High-speed PVL hand cutting (by divers) 

Special procedures developed for each cutting task

Strand Jack Solution

Heavy lifting specialist Sarens deployed 16 units of 450/650-ton strand jack combinations to lower the MOAB onto the transport barge. This was the first time Sarens APAC had used a strand jack solution for a decommissioning task.

 

3

 

 

3. Advantages of a Drilling-Free Plan: Key Benefits

Cost-effectiveness

By avoiding the use of heavy lift vessels and drilling rigs, the project achieved significant cost savings. Combining oil and gas industry experience with salvage thinking has proven to be key to cost-effective execution.

The no-rig approach eliminates the following costs:

Drilling rig mobilization and day-rate costs

Heavy-lift vessel charter costs

Associated marine support vessel requirements

Project efficiency

Faster mobilization and demobilization

Reduced offshore personnel requirements

Streamlined operations without rig constraints

Safety

Fewer personnel required offshore

ROV-assisted cutting reduced diver exposure

Remote operations minimized high-risk zone occupancy

Environmental sustainability

Rig-to-reef repurposing: The jacket was cut at -55 meters and laid on the seabed as artificial reef structures

Reduced carbon footprint: Fewer vessels meant lower fuel consumption and emissions

Marine ecosystem enhancement: The reef structures promote biodiversity, sustainable fisheries, and ecotourism |

Minimize platform interference

The rig-less solution executed wellhead recovery operations without disrupting platform infrastructure. The compact, modular approach was ideal for the space-constrained MOAB.

 

4

 

The 2025 Maera Terengganu South Angsi Alpha decommissioning project in Malaysia proves that rigless decommissioning is not just a concept - it's a proven, scalable, and cost-effective reality. 